Insights · Naples and Collier County
Who issues your pool permit inside the City of Naples and on Marco Island?
Owners inside the city regularly guess wrong about who signs their pool permit. The mailing address says Naples, the county is Collier, and the contractor says not to worry about it. Then the application lands at the wrong office, on the wrong form, and the job stops on day one. Old Naples, Port Royal, Aqualane Shores and the rest of the city grid report to the City of Naples Building Department. Marco Island reports to its own Building Services Division. Only the unincorporated rest of the county reports to Collier County. This guide was built by reading the two cities' own building pages side by side and setting them next to the county rules our other permit guides already cover.
A permitting jurisdiction is the government whose building department reviews, issues and inspects the permit for a parcel. The three this site's readers deal with are the City of Naples Building Department inside the city limit (City of Naples Building Department, 2026)1, the City of Marco Island Building Services Division on the island (City of Marco Island Building Services, 2026)7, and Collier County Growth Management Community Development in the unincorporated county (Collier County Growth Management Community Development, 2025)11. The parcel decides, not the postal address.
The short version
Who issues your pool permit inside the City of Naples and on Marco Island?
The addresses this site serves report to one of three permitting authorities, and they are not interchangeable. The City of Naples states that its Building Department enforces the Florida Building Code through the review and inspection of construction permits (City of Naples Building Department, 2026)1. Marco Island states that its Building Services Division issues permits, reviews plans and inspects projects, with a state-certified Building Official at its head (City of Marco Island Building Services, 2026)7. Everything outside those two city limits is unincorporated Collier County, whose pool application is the form our other permit guides describe (Collier County Growth Management Community Development, 2025)11.
This matters on day one. A contractor who says "we will pull the permit" has to pull it from the right office, through that office's portal. The City of Naples takes every application electronically through its Public Portal (City of Naples Building Department, 2026)4, Marco Island through its Civic Access Portal (City of Marco Island Building Services, 2026)7, and the county on its PRSPL pool form (Collier County Growth Management Community Development, 2025)11. An application filed with the wrong one is not late. It is no application.
Every permit guide on this site before this one described unincorporated Collier County and said so. This one covers the two cities, read first-hand from their own building department pages (City of Naples Building Department, 2026)1 (City of Marco Island Building Services, 2026)7. North of the county line, pool permits in Bonita Springs, Estero and Fort Myers covers the Lee offices the same way.
How do you tell which jurisdiction your address is in?
The City of Naples Building Department's own address is 295 Riverside Circle, Naples, FL 34102 (City of Naples Building Department, 2026)1, and that is the ZIP code most people picture when they hear Old Naples. The same postal name runs across neighborhoods that report to the county, which is why the mailing address is the wrong test. The question is whether the parcel sits inside the city limit.
The neighborhoods listed above are the ones this site treats as City of Naples pages, and the island is its own municipality with its own building office (City of Marco Island Building Services, 2026)7. If your neighborhood is on neither list, start with the county guide to whether pool resurfacing needs a permit in Collier County, and confirm the jurisdiction with the office before anything is filed.
When in doubt, ask the office rather than the contractor. The City of Naples publishes 239-213-5020 for permit questions (City of Naples Building Department, 2026)2, and Marco Island publishes 239-389-5059 and [email protected] (City of Marco Island Building Services, 2026)7. The Old Naples pool remodeling page and the Marco Island page cover what is different about the work itself in each place.
Not sure which side of the line you are on? Tell us the address and we will tell you which office it reports to and what that office asks for before the application goes in.

What pool work needs a permit in the City of Naples?
Read that trigger against a pool. A resurface alters and repairs the shell. A pump, light or heater swap replaces an electrical, mechanical or plumbing system. A new gas line is gas work. Each lands inside the 105.1 wording the City uses, and the City's exempt list, which runs from small repairs to drywall in a detached garage, has nothing about pools on it, and exempt work must still meet minimum code standards (City of Naples Building Department, 2026)2.
Heaters are the question we hear most, and the City answers it directly. Its building FAQ states that the City does require a permit and inspection of replacement pool heaters, including gas heaters, heat pumps and solar systems (City of Naples Building Department, 2026)6. A like-for-like swap is not an exception. Our gas pool heater installation page covers what that permit adds to the job inside the city.
The paperwork is split by trade. The City's 8th Edition forms include a dedicated Pool / Spa application alongside separate Electrical, Fuel / Gas, Mechanical and Plumbing forms, with a submittal checklist to review before filing (City of Naples Building Department, 2026)5. Every application is entered electronically through the City of Naples Public Portal (City of Naples Building Department, 2026)4, and applications submitted on or after December 31, 2023 must comply with the 8th Edition Florida Building Code (City of Naples Building Department, 2026)1.
Does the $7,500 HB 803 exemption work the same in the city, on Marco Island and in the county?
Start with the parts that agree. The City of Naples states that effective July 1, 2026 it is required by state law to exempt owners of single-family dwellings, and their contractors, from a building permit for work valued at less than $7,500 (City of Naples Building Department, 2026)3. Marco Island labels its version Minor Residential Work Valued Under $7,500 and ties it to F.S. 553.79(1)(g) (City of Marco Island Building Services, 2026)9. Collier County's page says certain qualifying work valued under $7500.00 will be exempt (Collier County Growth Management Community Development, 2026)13.
The bill behind the cities' wording is separate paper. The Florida Senate records CS/CS/HB 803 as Chapter Law 2026-63 with an effective date of July 1, 2026, and the bill page states no dollar figure (Florida Senate, 2026)12. Each office publishes its own threshold on its own page, so this article cites each page for its own number. Our guide to the exemption in Collier County explains why that matters.
The exclusions match too. The City of Naples lists electrical, plumbing, mechanical, gas and structural work, and any work on a property partially or entirely within a flood hazard area, as not eligible regardless of cost, and says pool barriers and fences count as structural (City of Naples Building Department, 2026)3. Marco Island publishes the same six categories without the pool barrier example (City of Marco Island Building Services, 2026)8. The City of Naples and Collier County both prohibit dividing one project to get under the cap (City of Naples Building Department, 2026)3 (Collier County Growth Management Community Development, 2026)13. What differs is the path and the paper at the end.
| Question | Unincorporated Collier County | City of Naples | Marco Island |
|---|---|---|---|
| Who issues the permit | Collier County Growth Management Community Development (Collier County Growth Management Community Development, 2025)11 | City of Naples Building Department, 295 Riverside Circle (City of Naples Building Department, 2026)1 | City of Marco Island Building Services Division, 1310 San Marco Rd, Suite A (City of Marco Island Building Services, 2026)7 |
| How you request the exemption | A written request reviewed by county staff (Collier County Growth Management Community Development, 2026)13 | A written request with a copy of the contract, in person, by email or through the portal (City of Naples Building Department, 2026)3 | Online through the permitting portal, with the contract attached (City of Marco Island Building Services, 2026)8 |
| Fee printed on the page | None stated on the page we read (Collier County Growth Management Community Development, 2026)13 | None stated on the exemption page; permit fees follow City Ordinance Sec. 16-52 (City of Naples Building Department, 2026)4 | A $40 exemption fee, paid online (City of Marco Island Building Services, 2026)8 |
| What you get back | A letter of exemption if approved (Collier County Growth Management Community Development, 2026)13 | Not stated on the page we read; the City says it has no legal duty for work performed under the exemption (City of Naples Building Department, 2026)3 | Not stated on the page we read (City of Marco Island Building Services, 2026)8 |
| Flood hazard area | The property may not be in a flood hazard area (Collier County Growth Management Community Development, 2026)13 | Work on a property partially or entirely within a flood hazard area is not eligible, and all permitted SFHA work needs an Elevation Certificate or the City FEMA form (City of Naples Building Department, 2026)34 | Applies only to properties not in a Special Flood Hazard Area, per the 2024 Flood Hazard Map (City of Marco Island Building Services, 2026)8 |
| Trade exclusions | No structural, mechanical, electrical, plumbing or gas work (Collier County Growth Management Community Development, 2026)13 | Electrical, plumbing, mechanical, gas and structural work excluded; pool barriers and fences named as structural (City of Naples Building Department, 2026)3 | Electrical, plumbing, mechanical, gas and structural work excluded, with no pool example given (City of Marco Island Building Services, 2026)8 |
| Splitting a project | Prohibited (Collier County Growth Management Community Development, 2026)13 | Prohibited; the exemption applies only to complete, single projects (City of Naples Building Department, 2026)3 | Not quoted on the page we read; ask the office (City of Marco Island Building Services, 2026)8 |
| Who it covers | Single family detached structures only (Collier County Growth Management Community Development, 2026)13 | Owners of single-family dwellings and their contractors (City of Naples Building Department, 2026)3 | Single-family properties, per the page title (City of Marco Island Building Services, 2026)8 |
What changes when the property is in a Special Flood Hazard Area?
Marco Island puts it in one line: the exemption applies only to properties not located in a Special Flood Hazard Area, permit requirements remain in effect inside one, and the page points to the city's 2024 Flood Hazard Map (City of Marco Island Building Services, 2026)8. The City of Naples reaches the same result through its exclusions, which name any work on a property located partially or entirely within a flood hazard area as defined by the Florida Building Code (City of Naples Building Department, 2026)3.
Inside the City of Naples the flood zone also changes the application itself. The City states that all permitted work within the SFHA requires either an Elevation Certificate showing the structure complies with current flood code or a completed City FEMA form submitted with the application (City of Naples Building Department, 2026)4. That is a document to find or commission before the application goes in, not after it comes back. Whether a remodel crosses the substantial improvement line is covered in Naples flood zones and substantial improvement.
Marco Island adds a note about larger projects. Its exemptions page says new construction, substantial improvements and certain repair projects must comply with floodplain regulations, which may include elevating structures, flood-resistant construction methods and floodplain development permits (City of Marco Island Building Services, 2026)8. Whether a pool remodel bundled with a house renovation crosses that line is the office's call, not the contractor's. A full pool also rides out a storm better than an empty one, which our guide to pool water levels before a hurricane covers.
The island's water is its own subject too. What Marco Island Utilities publishes about its supply, and what that means on fill day, is in Marco Island tap water and a new pool finish.

What does Marco Island ask for that the county does not?
The portal comes first. Marco Island states that to obtain a permit you must use its Civic Access Portal, and that inspection requests go through the same portal (City of Marco Island Building Services, 2026)7. Its Permitting Information page lists Contractor Registration Instructions, Contractor License / Insurance Update Instructions and an Early Permit Start Request process for non-emergency repairs (City of Marco Island Building Services, 2026)9.
The clock is specific. Inspections run Monday through Friday, 7:00 am to 5:00 pm, and the scheduling cutoff is 4:30 pm the day prior to the requested date (City of Marco Island Building Services, 2026)7. The city also offers remote video inspections for the sewer tap and the exterior gas rough (City of Marco Island Building Services, 2026)7.
Barriers and paperwork carry their own lines. The city says a licensed contractor, permit and inspection are required for screen enclosures and fences used as pool barriers, and points owners to the CPSC Safety Barrier Guidelines for Home Pools, Publication 362 (City of Marco Island Building Services, 2026)7. For most construction or remodeling projects a Notice of Commencement must be recorded with the Clerk of the Circuit Court before work begins, with a copy posted at the job site (City of Marco Island Building Services, 2026)7. Our screen enclosure permit guide covers the county side of the cage.
Two more things. Residential plan review applies only to single-family residences and duplexes; a condominium, although residential, requires a Multi-Family or Commercial permit (City of Marco Island Building Services, 2026)10. The city lists a Pool Spa guide among its plan review guides and calls them general references rather than definitive instructions (City of Marco Island Building Services, 2026)10; we did not open it, so we do not quote it. And if your community has an association, its approval belongs before the application, not after.
How does the permit office check the contractor?
What the office checks is the application in front of it, filed through its portal (City of Marco Island Building Services, 2026)7. Whether the scope in your contract matches the contractor's license class is a separate question, and it is yours. The office does not read your contract for you, and it does not tell you whether the person on the form is the person who will be on site.
Our guide to checking a Florida pool contractor's license walks through the four records to read, and the first is the easiest. Fla. Stat. 489.119(5)(b) requires the registration or certification number to appear in each offer of services, business proposal, bid, contract or advertisement, regardless of medium (Florida Statutes, 2024)14. A quote that arrives without a number has already told you something.
Insurance is the half no public register confirms. Marco Island keeps a contractor's license and insurance on file through its portal and publishes instructions for updating them (City of Marco Island Building Services, 2026)9, but that file is the city's, not yours. Ask for the certificate of insurance and verify it with the agency named on it. The note below is Clayton's own statement of what his license covers; the class and status sit on the public DBPR record, and our about page carries the company's own number.
What should you settle before the contractor applies?
Which office, and who applies. The office is decided by the parcel, as above. Who applies matters because both cities let either the property owner or the contractor request the exemption (City of Naples Building Department, 2026)3 (City of Marco Island Building Services, 2026)8, and the person who applies is the person the office writes back to. Settle it in the contract.
The contract and its value. Both city exemption routes ask for the written contract or other documentation showing the nature and value of the work (City of Naples Building Department, 2026)3 (City of Marco Island Building Services, 2026)8, and Collier County reviews a written request the same way (Collier County Growth Management Community Development, 2026)13. A verbal scope cannot be filed. A written one also lets you read it for the words electrical, plumbing, mechanical, gas and structural before the office does.
The flood status and the association. Marco Island points to its 2024 Flood Hazard Map (City of Marco Island Building Services, 2026)8, and the City of Naples wants the Elevation Certificate or City FEMA form in the application (City of Naples Building Department, 2026)4. Check the parcel before anything is drawn. If an association has to approve the work, get that first; it is a separate approval from a separate body.
The Notice of Commencement. Marco Island says that for most construction or remodeling projects it must be recorded with the Clerk of the Circuit Court before work begins, with a copy posted at the job site (City of Marco Island Building Services, 2026)7. What the permit path costs is driven by which office, how many trade applications the scope needs and whether SFHA paperwork is involved; the only figure either city prints on the pages we read is Marco Island's $40 exemption fee (City of Marco Island Building Services, 2026)8. Pool remodeling in Naples starts with this checklist.
Ask Clayton
Questions this article usually prompts
Tap a question. Clayton replies himself, here and on the phone.
Tap a question to ask
If this is the situation you are in
The whole project: How does a Naples pool resurfacing project run, from first decision to first month? →The whole project: What does renovating a Naples pool deck involve, from the first crack to the last coat of sealer? → Pool remodeling in Naples, handled as one project →References
- City of Naples Building Department, Building (8th Edition FBC effective December 31, 2023; office address), read 1 November 2026
- City of Naples Building Department, When do I need a Permit?, read 1 November 2026
- City of Naples Building Department, Building Permit Exemptions for Residential Properties (HB803), read 1 November 2026
- City of Naples Building Department, Building Permit Forms & Fees (electronic submittal; SFHA Elevation Certificate or City FEMA form), read 1 November 2026
- City of Naples Building Department, Permit Application Forms, 8th Edition (effective 12/31/2023), read 1 November 2026
- City of Naples Building Department, Frequently Asked Questions, Building: "Do pool heaters require a permit?", read 1 November 2026
- City of Marco Island Building Services, Building Services (portal, office, inspection hours, pool barriers, Notice of Commencement), read 1 November 2026
- City of Marco Island Building Services, Building Permit Exemptions for Single-Family Properties, read 1 November 2026
- City of Marco Island Building Services, Permitting Information (contractor registration, license and insurance updates, exempt work list), read 1 November 2026
- City of Marco Island Building Services, Residential Plan Review, read 1 November 2026
- Collier County Growth Management Community Development, Swimming Pool permit application (PRSPL), form dated 27 January 2025
- Florida Senate, CS/CS/HB 803 Building Permits and Inspections, Chapter Law 2026-63, effective 1 July 2026
- Collier County Growth Management Community Development, Work Exempt from Permit (PRAD), retrieved 13 August 2026
- Florida Statutes, Title XXXII, Chapter 489, Section 489.119: Business organizations; qualifying agents (2024)